A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?

  • A. 1.25 days
  • B. 1.33 days
  • C. 2 days
  • D. This cannot be determined without knowing the velocity.
Show Suggested Answer Hide Answer

Suggested Answer: B

Comments

jleo85
2 weeks ago
Why is 1.33 ?
upvoted 1 times
...