Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
Location Chicago IL, USA

Exam ASM topic 1 question 28 discussion

Actual exam question from Exin's ASM
Question #: 28
Topic #: 1
[All ASM Questions]

Inexperienced Agile teams tend to overestimate how much they will achieve in the first Sprint.
Which project management activity will be most important in this case?

  • A. Determine the Velocity of the Team and plan accordingly
  • B. Use Planning Poker to get a reliable estimate
  • C. Use Stakeholder Management to manage expectations
Show Suggested Answer Hide Answer

Suggested Answer: C

Comments

kschinchin
1 week, 3 days ago
Shd be B
upvoted 1 times
...
TORA
3 months, 4 weeks ago
I can't see how stakeholder management should solve this problem. Determine a velocity and plan accordingly is the only answer which is a solution to the problem.
upvoted 1 times
...

SaveCancel