A playbook contains five tasks in total. An administrator executed the playbook and four out of five tasks finished successfully, but one task failed. What will be the status of the playbook after its execution?
Correct Ans: A
Playbook jobs that include one or more failed tasks are labeled as Failed in Playbook Monitor.
FortiAnalyzer_7.0_Study Guide page No: 247
The current status of the job. Statuses include:
Running: The job is currently running.
Success: The job has finished with all tasks completed successfully.
Failed: The job has finished with one or more tasks failing to complete successfully
A) FortiAnalyzer_7.0_Study_Guide-Online.pdf page 247: Playbook jobs that include one or more failed tasks are labeled as Failed in Playbook Monitor. A failed status, however, does not mean that all tasks failed. Some individual actions may have been completed successfully.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
wayne0926
Highly Voted 1 year, 6 months agoMarchrist
Most Recent 10 months, 3 weeks agoMarchrist
10 months, 4 weeks agochyeahhh
11 months, 3 weeks agodede1234
1 year, 4 months agolucient
1 year, 5 months agoilbartonicola
1 year, 5 months agoRonnie89
1 year, 6 months agoD10SJoker
1 year, 6 months ago