You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
Roygabib
9 months, 2 weeks agomeg002
11 months, 3 weeks agomith88
1 year, 5 months agopatitos
1 year, 8 months agoAbhyag
2 years agoMan4444
2 years agonicesiuhung
2 years, 1 month agoStillPatient
3 years, 5 months agoaktheraja
3 years, 8 months agoPooja
4 years, 7 months ago