Exam CSM-001 topic 1 question 87 discussion

Actual exam question from GAQM's CSM-001
Question #: 87
Topic #: 1
[All CSM-001 Questions]

The _____________ control model requires that every piece of work be completely understood.

  • A. Defined process
  • B. Empirical Process
  • C. Incremental Process
  • D. Six Sigma. Process)
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
nicesiuhung
2 years, 6 months ago
why B, i think it is A
upvoted 1 times
...
mkundal
3 years, 6 months ago
defined process control every piece of work is understood. In Scrum, an empirical process is implemented where progress is based on observation and experimentation instead of detailed, upfront planning and defined processes. correct ans /;A
upvoted 1 times
...
Snownoodles
4 years, 1 month ago
"Empirical process control expects the unexpected, while defined process control expect every piece of work to be completely understood in upfront". The correct answer is A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...