Which action is included in the Control Costs process?

  • A. Identify how the project costs will be planned, structured, and controlled
  • B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
  • C. Develop an approximation of the monetary resources needed to complete project activities
  • D. Monitor cost performance to isolate and understand variances from the approved cost baseline
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...