Exam CSM-001 topic 1 question 26 discussion

Actual exam question from GAQM's CSM-001
Question #: 26
Topic #: 1
[All CSM-001 Questions]

Which of the following is reflected in a Sprint Burn down Chart?

  • A. Team Members Name
  • B. Number of Product Backlog Items Completed
  • C. Number of Tasks Remaining
  • D. Work Hours Remaining
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mi_Windsor
10 months, 1 week ago
That will be C
upvoted 1 times
...
Teejob
1 year, 2 months ago
The Scrum Burndown Chart is a visual measurement tool that shows the completed work per day against the projected rate of completion for the current project release
upvoted 1 times
...
Ranita
1 year, 5 months ago
Selected Answer: C
Correct answer is C
upvoted 2 times
...
donpet15
1 year, 5 months ago
C is the correct answer
upvoted 2 times
...
Abhyag
2 years, 4 months ago
D. Sprint burndown is a graphical representation of the estimated effort-hours remaining for a given period of time during a Sprint.
upvoted 1 times
...
Bakayalo
2 years, 5 months ago
According to scrum.org Burn-down Chart: a chart which shows the amount of work which is thought to remain in a backlog. D is the answer
upvoted 2 times
Bakayalo
2 years, 5 months ago
Typo,it is C
upvoted 1 times
...
...
nicesiuhung
2 years, 5 months ago
should be D
upvoted 1 times
...
nicesiuhung
2 years, 5 months ago
C is the correct Answer
upvoted 2 times
...
Kamalindya
3 years, 4 months ago
C. "The Sprint Burndown Chart is a graph that depicts the amount of work remaining in the ongoing Sprint." SBOK 9.6.3.2
upvoted 2 times
...
KartMages
3 years, 8 months ago
This Should be C. The chart shows the amount of work remaining. Chart shows Team progress towards the Sprint Goal, not in terms of time spent but in terms of how much work remains.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...