Exam CSM-001 topic 1 question 10 discussion

Actual exam question from GAQM's CSM-001
Question #: 10
Topic #: 1
[All CSM-001 Questions]

You are the new Scrum Master at a company currently doing RUP in three month iterations. Your current task in switching from RUP to Scrum is to define how long the Sprint cycle should be. In what units of time should you define the sprint cycle?

  • A. A fixed amount of months
  • B. A fixed amount of weeks, excluding holidays
  • C. A fixed amount of days
  • D. A fixed amount of hours
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Mi_Windsor
8 months, 2 weeks ago
B , in weeks
upvoted 1 times
...
brightblue
8 months, 3 weeks ago
B - in weeks
upvoted 1 times
...
Mi_Windsor
9 months, 1 week ago
B - in weeks
upvoted 1 times
...
Mikhil16
1 year, 1 month ago
Shouldn't it be weeks or even month since SCRUM guide outlines all time box framework for 1 month or 4 weeks sprint cycle?
upvoted 2 times
...
nancyqing
1 year, 2 months ago
Shouldn't it be weeks??
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...