When is a Mode Conditioning Patch Cable required?

  • A. A 10GBase-LR Transceiver is operated with 62.5/125 cables up to 500 m.
  • B. A 10GBase-LX4 Transceiver is operated with 62.5/125 cables up to 2 km.
  • C. A 1000Base-LX Transceiver is operated with 62.5/125 cables up to 500 m.
  • D. A 1000Base-SX Transceiver is operated with 62.5/125 cables up to 500 m.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
emankcin01
1 month ago
Selected Answer: C
Gigabit-LX transceivers, since they are designed to operate with both singlemode and multimode cable, do not provide the transmission conditioning internally. Thus, under certain circumstances, depending on the cable used and the lengths of the cable runs, an external Mode Conditioning Patch Cord may need to be installed between the Gigabit-LX transmitting device and the multimode network cable to provide the transmission conditioning
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...