D is correct.
Warning is the first level and Action is the second level. When the second level is breached (upper or lower levels) then work orders are triggered.
For GAUGE meters you can also enter the upper/lower warning limits
https://maximosecrets.com/2022/07/15/meters-meter-groups-and-condition-monitoring-2/#condition-monitoring
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Stfan
3 months, 3 weeks agoHyrule_Warrior
3 months, 3 weeks agoHyrule_Warrior
3 months, 3 weeks agoClem2
6 months, 1 week agoHelioreis
8 months ago