Teh correct answer is C. the Work Order target start date + the Job Plan duration.
The Joblan has no Start en finish dates
The pm has no target finish date
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
fdeghadi
10 months agoClem2
11 months, 3 weeks agostefun75
1 year ago