The only possible correct anwer should be C.
A is wrong, Job Plan Revision field is always read only
B is wrong Job Plan field is read only for approved work orders.
D. is wrong, Remove Work Plan from the More Actions generate the error: BMXAA4672E - Work plan must be editable to remove it.
I think the answer is C "Create a follow-up work order..." because it is not possible to remove task on an Appr work order. Since remove Job Plan will remove all task, the answer D is not correct
https://www.ibm.com/support/knowledgecenter/SSBLW8/com.ibm.mbs.doc/wotrack/c_wo_mgmt_plans.html
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
beanz998
2 years, 8 months agofdeghadi
2 years, 9 months agolucafranco
3 years, 5 months agoeverwelwisher
3 years, 10 months agoeverwelwisher
3 years, 10 months agoSindhu_Tyro
4 years, 6 months agoSindhu_Tyro
4 years, 6 months agoLavoisier
4 years, 9 months ago