Actual exam question from IIA's IIA-CIA-Part2
Question #: 72
Topic #: 3
[All IIA-CIA-Part2 Questions]

Because of an abundance of high priority requests from management, an internal audit activity no longer has the resources to meet all of its commitments contained in the annual audit plan. Which of the following would be the best course of action for the chief audit executive to follow?

  • A. Continue with the plan and seek opportunities to adjust priorities and reallocate resources.
  • B. Present a reassessment of the plan to the board and senior management for consideration.
  • C. Reassess the plan and either cancel or divert resources away from the lowest priority activities.
  • D. Advise the board immediately and seek their support for additional resources to meet the needs of the plan.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Disin
11 months, 1 week ago
shouldn't it be D?
upvoted 1 times
...
balqis32
1 year, 4 months ago
cannot simply take all management request. need to perform reassessment before incorporated in the iap
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...