Refer to the exhibit. The figure below shows the network diagram for the activities of a large project. What is the shortest number of days in which the project can be completed?
Activity: B-D= 12+9=21
Activity A-C-D= 10+8+9=27
Activity A-E= 10+12=22
Critical Path= Longest Path among all possible ways to reach final destination (which is 27 days for A-C-D)