Question #: 182
Topic #: 1
[All IIA-CIA-Part3 Questions]

According to IIA guidance, which of the following is a typical risk associated with the tender process and contracting stage of an organization's IT outsourcing life cycle?

  • A. The process is not sustained and is not optimized as planned.
  • B. There is a lack of alignment to organizational strategies.
  • C. The operational quality is less than projected.
  • D. There is increased potential for loss of assets.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
lely55
2 weeks ago
Selected Answer: D
Yomang is correct. Read the GTAG, it’s mentioned.
upvoted 1 times
...
Domiii
3 months, 3 weeks ago
Selected Answer: B
According to IIA (Institute of Internal Auditors) guidance, the typical risk associated with the tender process and contracting stage of an organization's IT outsourcing life cycle is option B. There is a lack of alignment to organizational strategies. During the tender process and contracting stage of IT outsourcing, organizations may face the risk of not aligning the outsourced IT services with the organization's overall strategies and objectives. This means that the selected vendor or service provider may not fully understand or be able to support the organization's strategic goals, resulting in potential inefficiencies, conflicts, or missed opportunities.
upvoted 3 times
...
yomang
2 years, 8 months ago
It is definitely D. Please check out GTAG 7. A is clearly mentioned under the "Monitoring and Reporting" stage. B is clearly mentioned under the "Strategic Fit and Sourcing Evaluation" stage. C is clearly mentioned under the "Implementation and Transition" stage. Although "loss of assets" is a risk listed under multiple other stages, it is the only one of these four options that is listed under the "Tender Process and Contracting" stage - as shown, the other three options are clearly risks under different stages. Since this question is asking which of the four options below is a risk under the "Tender Process and Contracting" stage, it has to be D, because the other three are clearly stated in other stages.
upvoted 4 times
...
Java_Girl
2 years, 9 months ago
The correct answer should be C
upvoted 1 times
yomang
2 years, 8 months ago
Would you mind providing an explanation and/or source for your answer?
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...