Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam CBAP topic 1 question 440 discussion

Actual exam question from IIBA's CBAP
Question #: 440
Topic #: 1
[All CBAP Questions]

A business analyst (BA) was developing an outline of the timing of business analysis activities with the project manager. What factors may impact the timing of the activities the BA is performing?

  • A. Solution design
  • B. Project manager's experience
  • C. Contract terms
  • D. Project sponsor interest
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://www.slideshare.net/MSaifurRahmanMBAPMP/cbap-babok-v3-notes

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
siliconvalleykam
Highly Voted 3 years, 3 months ago
"• constraints such as contract terms or regulatory deadlines." BABOK - C - Contract terms
upvoted 8 times
...
Omojesun
Highly Voted 3 years, 3 months ago
C, I think.
upvoted 5 times
Chyka
3 years, 3 months ago
C is Correct. Reference is on page 28
upvoted 4 times
...
...
Farooq_95
Most Recent 2 days ago
Selected Answer: C
As per BABOK v3 3.1.4.4, the timing of business analysis activities may be affected by • the availability of resources, • priority and/or urgency of the initiative, • other concurrent initiatives, or • constraints such as contract terms or regulatory deadlines. Hence, Contract terms mentioned here seems the appropriate answer. Logically, project sponsor interest or solution design does not directly impact the timelines of BA activities.
upvoted 1 times
...
Rabbitsfoot
1 month ago
Selected Answer: A
"Solution design" (option A) is the factor that directly impacts the timing of the activities the business analyst (BA) is performing. The solution design phase typically follows the business analysis phase, and the timing of BA activities may depend on when the solution design is finalized. Here's a brief explanation of why the other options are not directly related to the timing of BA activities: - Project manager's experience (option B): While the project manager's experience may influence overall project planning and management, it doesn't directly impact the timing of specific BA activities within the project timeline.
upvoted 1 times
Rabbitsfoot
1 month ago
- Contract terms (option C): Contract terms may define the scope of work, deliverables, and responsibilities, but they don't necessarily dictate the timing of BA activities unless specified in the contract. - Project sponsor interest (option D): The project sponsor's interest may influence project priorities and support, but it doesn't typically determine the timing of BA activities within the project schedule.
upvoted 1 times
...
...
JerryMag4
4 months, 1 week ago
C is the answer pls
upvoted 1 times
...
786NB786
2 years, 4 months ago
C=contract terms - pg 28 - The timing of business analysis activities can also be affected by: • the availability of resources, • priority and/or urgency of the initiative, • other concurrent initiatives, or • constraints such as contract terms or regulatory deadlines.
upvoted 3 times
...
DeepthiB
2 years, 4 months ago
Ans - C 3.1.4.4
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...