BABOK v2 pg 170
Analogous Estimation
Use of a similar project as the basis for developing estimates for the current project. It is
used when little is known. Analogous estimating is often used to develop a rough order of
magnitude (ROM) estimate, and is also known as “top-down” estimating. This is usually
done at the beginning of the project or project phase and more detailed estimates follow
as more is known.
The correct answer is D. Top-down estimate.
A top-down estimate is an estimate based on past projects or experiences, where the estimator uses historical data to predict the cost and/or duration of the current project. This approach involves using high-level, overall project metrics from previous projects to estimate the current project's costs and duration.
Top-down estimates are often used when there is limited information available about the current project, or when the project is similar to previous projects.
The other options are not correct because:
- A. Current estimate: This is an estimate based on the current project's specific details and requirements.
- B. Past project cost: This refers to the actual cost of a previous project, rather than an estimate.
- C. Past estimate: This refers to an estimate made in the past, rather than an estimate based on past projects.
D. Top-down estimate
A top-down estimate is based on past projects to predict the current cost and/or duration of the current project. It uses high-level information from similar previous projects to estimate the overall cost and schedule
I think D was selected as the answer in the context of estimating the current cost based on estimation performed early in the project life cycle when detailed information is limited and relies on high-level assumptions, analogous estimation, or historical data from similar projects.
Top Down: examining the components at a high level in a hierarchical
Breakdown. None of the options are correct.
Delphi estimation technique uses a combination of expert judgment and history.
Top down estimating approach deals with how long the project will take to completion then breaking them into various tasks.
Bottom up deals with estimating how long it take each sub task to complete
Top-down: examining the components at a high level in a hierarchical breakdown.
upvoted 4 times
...
This section is not available anymore. Please use the main Exam Page.CBAP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Demo311
4 days, 1 hour agoKEN_ELELEGWU
3 months, 2 weeks agoCBAPCohort6
6 months, 2 weeks agoRfcuenca
1 year, 3 months agoRfcuenca
1 year, 3 months agosubyottun
1 year, 4 months agoNuriaIzard
2 years, 7 months agoShreejith
2 years, 9 months agoNwazuluaru
2 years, 11 months agoElyonSenjo
3 years agosubha_CBAP
4 years, 3 months ago