Exam CBAP topic 1 question 288 discussion

Actual exam question from IIBA's CBAP
Question #: 288
Topic #: 1
[All CBAP Questions]

A project's change in scope is assessed and a newly assigned business analyst (BA) is unsure how to communicate the findings and final decision to the wider stakeholder group.
In which of the following can the BA find this information?

  • A. Stakeholder Communications Plan
  • B. Business case
  • C. Business policies
  • D. Governance approach
Show Suggested Answer Hide Answer

Suggested Answer: A

Comments

AngelShowri
4 days, 10 hours ago
Ans D. Pg. 39 Part of change control process. Determine how changes will be communicated: how proposed changes, changes under review, and approved, declined, or deferred changes will be communicated to stakeholders.
upvoted 3 times
...
rhsdeal
2 months ago
Why Not D? BABOK V-3 3.3.2 pg.37 Plan Business Analysis Governance: A governance process describes how approvals and prioritization decisions are made for requirements and designs. (...) When planning the governance approach, business analysts identify: (...) • who has the authority to approve changes, and • how changes will be documented and communicated.
upvoted 3 times
...