Exam CBAP topic 1 question 458 discussion

Actual exam question from IIBA's CBAP
Question #: 458
Topic #: 1
[All CBAP Questions]

The stakeholder of a new product that is in early adaptive development has requested a change to an approved feature. How should the business analyst (BA) handle this change?

  • A. Change the business analysis approach to predictive
  • B. Obtain formal approval through change request process
  • C. Add the feature to the product backlog for future prioritization
  • D. Include the requirement in the next iteration
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ccie_cbap
Highly Voted 2 years, 10 months ago
Answer C- There is a line in the question that refers to 'early adaptive development which directly means 'Adaptive development'. Change requests in adaptive approach are added to backlog for future prioritization.
upvoted 6 times
Farooq_95
1 week, 3 days ago
Even though the product is in early adaptive development, the changes proposed needs to be formally approved and then added to the product backlog as a feature to be developed in future. Otherwise, any irrelevant stakeholder may propose changes that will be added to product backlog which cause ambiguities or inconsistencies in future. The term Adaptive means changes can be accepted late in the development. As per BABOK v3 3.1.4.2, adaptive approaches favour defining requirements and designs through team interaction and gathering feedback on a working solution. This suggests that adaptive approach also require careful evaluation of feature before being added to product backlog.
upvoted 2 times
...
...
rupakarthik
Highly Voted 3 years ago
i believe its c. A predictive approach may indicate a more formal assessment of proposed changes. In predictive approaches, the impact of each change can be disruptive; the change can potentially generate a substantial reworking of tasks and activities completed in previous activities. An adaptive approach may require less formality in the assessment of proposed changes. While there may be reworking needed as a result of each change, adaptive approaches try to minimize the impact of changes by utilizing iterative and incremental implementation techniques. Page-92
upvoted 5 times
rupakarthik
3 years ago
since the question is about a feature, i believe C is right
upvoted 3 times
...
...
Rabbitsfoot
Most Recent 1 month ago
Selected Answer: B
change control process would apply for when any approved requirement changes
upvoted 1 times
...
Rfcuenca
3 months, 2 weeks ago
It’s impossible in adaptative development that the solution were B
upvoted 1 times
...
Adaobi_Oteks
1 year, 1 month ago
B- The new stakeholder wants a further change to a previously approved feature. This means the change request must be subject to another approval.
upvoted 2 times
...
binu801
2 years, 8 months ago
It's not clear who is the stakeholder and what's her influence. In an agile ( adaptive approach )C or D is the answer. If it is coming from a sponsor or product owner, generally it's taken in the next iteration. otherwise, it's added to the backlog. In a predictive ( waterfall ) approach B is the answer. as the question mentions adaptive cycle I will Go with D . However C is also a valid answer
upvoted 1 times
...
[Removed]
2 years, 10 months ago
Ans B according to me - Refer pg 39 - 3.3.4.2 Change control process - Determine the elements of the change request: identify the information to be included in a proposal to support decision making and implementation if it is approved. Another reference is pg - 95 - Business analysts work with key stakeholders to gain consensus on new and changed requirements, communicate the outcome of discussions, and track and manage the approval.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.