Exam CBAP topic 1 question 443 discussion

Actual exam question from IIBA's CBAP
Question #: 443
Topic #: 1
[All CBAP Questions]

During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the business analyst (BA).
The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:

  • A. stakeholder engagement plan
  • B. change control process
  • C. risk strategy
  • D. prioritization approach
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ccie_cbap
Highly Voted 2 years, 11 months ago
Option B- Change control process - Determine how changes will be communicated: how proposed changes, changes under review, and approved, declined, or deferred changes will be communicated to stakeholders.
upvoted 8 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...