Exam ECBA topic 1 question 19 discussion

Actual exam question from IIBA's ECBA
Question #: 19
Topic #: 1
[All ECBA Questions]

Which of the following activities are performed during the requirements life cycle management phase?

  • A. Elicit Requirements
  • B. Prioritize Designs
  • C. Trace Requirements
  • D. Maintain Attributes
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Throneroom
Highly Voted 1 year, 6 months ago
I think this question means which tasks are NOT performed in the Requirements and Life Cycle Management Tasks.
upvoted 10 times
...
Olutimi
Most Recent 4 months, 2 weeks ago
Answer is C; Trace requirement. The other tasks are maintain, prioritize, assess and approve.
upvoted 1 times
...
Only12go
7 months, 1 week ago
Answer is C - The knowledge area of requirements life cycle management involves five tasks that a business analyst needs to perform: trace requirements, maintain requirements, prioritise requirements, asses requirements changes, and approve requirements.
upvoted 1 times
...
Sourabh_Sharma
7 months, 2 weeks ago
Question seems to be incorrect, Elicit requirement is not part of RLCM rest all activities are performed during RLCM. Correct question should be which activity is “NOT” part of RLCM.
upvoted 1 times
...
muf33f3
11 months ago
All answers are correct except Elicitat Requirements. I agree with @Throneroom's comment
upvoted 1 times
...
Adnan8t2
12 months ago
Selected Answer: C
ANSWER: C Page 76 – BABOK V3 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.
upvoted 2 times
...
amrita0204
1 year, 1 month ago
I think it should be option C
upvoted 1 times
...
m4tim4ti
1 year, 1 month ago
Selected Answer: C
BABOK p. 76 The Requirements Life Cycle Management knowledge area includes the following tasks: • Trace Requirements: analyzes and maintains the relationships between requirements, designs, solution components, and other work products for impact analysis, coverage, and allocation.
upvoted 2 times
...
A_pe
1 year, 2 months ago
Selected Answer: C
I think Trace requirements is correct
upvoted 1 times
...
Hazemnz
1 year, 3 months ago
Selected Answer: C
BABOK page 76
upvoted 2 times
...
Hazemnz
1 year, 3 months ago
Selected Answer: C
BABOK page 93
upvoted 1 times
...
INDEAVR
1 year, 6 months ago
I think the correct answer is "Trace Requirements" as the other ones I would classify as misleading - e.g. it's requirements prioritization, not design prioritization.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.