You are the risk official in Bluewell Inc. You are supposed to prioritize several risks. A risk has a rating for occurrence, severity, and detection as 4, 5, and 6, respectively. What Risk Priority Number (RPN) you would give to it?
Suggested Answer:A🗳️
Steps involving in calculating risk priority number are as follows: ✑ Identify potential failure effects ✑ Identify potential causes ✑ Establish links between each identified potential cause ✑ Identify potential failure modes ✑ Assess severity, occurrence and detection ✑ Perform score assessments by using a scale of 1 -10 (low to high rating) to score these assessments. ✑ Compute the RPN for a particular failure mode as Severity multiplied by occurrence and detection. RPN = Severity * Occurrence * Detection Hence,
RPN = 4 * 5 * 6 - = 120 Incorrect Answers: B, C, D: These are not RPN for given values of severity, occurrence, and detection.
To calculate the Risk Priority Number (RPN), you can use the formula:
RPN = Occurrence x Severity x Detection
In this case, the values are:
Occurrence = 4
Severity = 5
Detection = 6
So, RPN = 4 x 5 x 6 = 120
Therefore, the correct RPN for this risk is A. 120.
This section is not available anymore. Please use the main Exam Page.CRISC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SuperMax
9 months, 4 weeks agoGhostclown
1 year, 5 months agoChemngoremmercy
1 year, 9 months agoldl
2 years, 4 months ago