Which of the following is the MOST important objective of embedding risk management practices into the initiation phase of the project management life cycle?
A.
To deliver projects on time and on budget
B.
To assess inherent risk
C.
To assess risk throughout the project
D.
To include project risk in the enterprise-wide IT risk profile