Question #: 1223
Topic #: 1
[All CRISC Questions]

Which of the following is MOST important when conducting a post-implementation review as part of the system development life cycle (SDLC)?

  • A. Verifying that project objectives are met
  • B. Reviewing the project initiation risk matrix
  • C. Identifying project cost overruns
  • D. Leveraging an independent review team
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CbtL
8 months, 1 week ago
Selected Answer: A
Agree with A.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...