Before the release of a new application into an organization's production environment, which of the following should be in place to ensure that proper testing has occurred and rollback plans are in place?
While standardized change requests are important for documentation and tracking, a change approval board provides the necessary oversight and decision-making authority to review all changes, ensuring that proper testing and rollback plans are in place.
Before the release of a new application into an organization's production environment, having a Change Approval Board in place is important to ensure that proper testing has occurred and rollback plans are in place. The CAB is responsible for reviewing and approving changes to the IT environment, including new applications or updates, to ensure that they meet quality standards and do not adversely impact the production environment.
This section is not available anymore. Please use the main Exam Page.CISA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Swallows
10 months, 1 week agoRachy
1 year, 4 months agoFAGFUR
1 year, 6 months agosaado9
2 years ago