Question #: 545
Topic #: 1
[All CISA Questions]

Which of the following procedures for testing a disaster recovery plan (DRP) is MOST effective?

  • A. Performing a quarterly tabletop exercise
  • B. Reviewing documented backup and recovery procedures
  • C. Performing an unannounced shutdown of the computing facility after hours
  • D. Testing at a secondary site using offsite data backups
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
spar2kle
9 months, 4 weeks ago
Why not C
upvoted 2 times
...
Changwha
12 months ago
D. Testing at a secondary site using offsite data backups
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.