Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

  • A. Activity duration estimates
  • B. Risk management plan
  • C. Cost management plan
  • D. Activity cost estimates
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
The activity cost estimates review is valuable in identifying risks as it provides a quantitative assessment of the expected cost to complete the scheduled activities and is expressed as a range, with a width of the range indicating the degrees of risk.
Incorrect Answers:
A: The activity duration estimates review is valuable in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk.
B: This is the output of plan risk management process. A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.
C: The cost management plan sets how the costs on a project are managed during the project's lifecycle. It defines the format and principles by which the project costs are measured, reported, and controlled. The cost management plan identifies the person responsible for managing costs, those who have the authority to approve changes to the project or its budget, and how cost performance is quantitatively calculated and reported upon.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SuperMax
9 months, 1 week ago
Selected Answer: D
D. Activity cost estimates Activity cost estimates provide a quantitative assessment of the likely cost to complete the scheduled activities, making them a useful input for identifying risks in the project. These estimates can help project managers understand the potential financial impacts of various risks on the project's budget and help in risk identification and assessment
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...