Question #: 242
Topic #: 1
[All CRISC Questions]

Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?

  • A. Functional baseline
  • B. Allocated baseline
  • C. Product baseline
  • D. Developmental baseline
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Allocated baseline identifies the specifications that meet the approved requirements.
Incorrect Answers:
A: Functional baseline identifies the initial specifications before any changes are made.
C: Product baseline identifies the minimal specification required by the resource to meet business outcomes.
D: Developmental baseline identifies the state of the resources as it is developed to meet or exceed expectations and requirements.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SuperMax
9 months, 1 week ago
Selected Answer: B
B. Allocated baseline The allocated baseline is the set of specifications and requirements that have been allocated to specific resources or components of a project. It represents how the overall requirements are divided and assigned to different parts of the project or specific resources. This helps ensure that the resources are aligned with the approved requirements.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...