You are the project manager of RFT project. You have identified a risk that the enterprise's IT system and application landscape is so complex that, within a few years, extending capacity will become difficult and maintaining software will become very expensive. To overcome this risk, the response adopted is re- architecture of the existing system and purchase of new integrated system. In which of the following risk prioritization options would this case be categorized?