You are the project manager of a project in Bluewell Inc. You and your project team have identified several project risks, completed risk analysis, and are planning to apply most appropriate risk responses. Which of the following tools would you use to choose the appropriate risk response?

  • A. Project network diagrams
  • B. Cause-and-effect analysis
  • C. Decision tree analysis
  • D. Delphi Technique
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Decision tree analysis is a risk analysis tool that can help the project manager in determining the best risk response. The tool can be used to measure probability, impact, and risk exposure and how the selected risk response can affect the probability and/or impact of the selected risk event. It helps to form a balanced image of the risks and opportunities connected with each possible course of action. This makes them mostly useful for choosing between different strategies, projects, or investment opportunities particularly when the resources are limited. A decision tree is a decision support tool that uses a tree-like graph or model of decisions and their possible consequences, including chance event outcomes, resource costs, and utility.
Incorrect Answers:
A: Project network diagrams help the project manager and stakeholders visualize the flow of the project work, but they are not used as a part of risk response planning.
B: Cause-and-effect analysis is used for exposing risk factors and not an effective one in risk response planning. This analysis involves the use of predictive or diagnostic analytical tool for exploring the root causes or factors that contribute to positive or negative effects or outcomes.
D: Delphi technique is used for risk analysis, i.e., for identifying the most probable risks. Delphi is a group of experts who used to rate independently the business risk of an organization. Each expert analyzes the risk independently and then prioritizes the risk, and the result is combined into a consensus.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SuperMax
6 months, 2 weeks ago
Selected Answer: C
C. Decision tree analysis Decision tree analysis is a tool that helps in selecting appropriate risk responses by evaluating various possible outcomes of a risk and the potential impact of different response strategies. It allows you to assess the probabilities and consequences associated with each response and make informed decisions about which risk response to implement. This is a valuable technique in risk management and helps in making decisions based on a quantitative analysis of the risks and their potential consequences.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago