Question #: 980
Topic #: 1
[All CISM Questions]

Which of the following would be the GREATEST concern with the implementation of key risk indicators (KRIs)?

  • A. Inability to measure KRIs
  • B. Poorly defined risk appetite
  • C. Overly specific KRI definitions
  • D. Complex organizational structure
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlexJacobson
Highly Voted 9 months, 3 weeks ago
Selected Answer: B
If you don't have clearly defined risk appetite, how would you measure the level of current risk for an activity?
upvoted 5 times
...
jcisco123
Most Recent 10 months ago
Selected Answer: A
A. Inability to measure KRIs
upvoted 1 times
...
richck102
1 year ago
Selected Answer: B
B. Poorly defined risk appetite
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...