An IT risk threat analysis is BEST used to establish:

  • A. risk scenarios.
  • B. risk maps.
  • C. risk ownership.
  • D. risk appetite.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
K5000ism
11 months ago
Selected Answer: A
A. risk scenarios. An IT risk threat analysis involves identifying potential threats to IT systems, applications, and data. Through this analysis, various risk scenarios can be identified, where a risk scenario typically involves a combination of a threat, vulnerability, and potential impact. Establishing risk scenarios helps organizations understand and prioritize potential risks in the IT environment, allowing for the development of effective risk management strategies and controls.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...