exam questions

Exam CGEIT All Questions

View all questions & answers for the CGEIT exam

Exam CGEIT topic 1 question 86 discussion

Actual exam question from Isaca's CGEIT
Question #: 86
Topic #: 1
[All CGEIT Questions]

The IT director of a large project-driven enterprise is concerned that all recently completed IT projects have exceeded their budgets. Which of the following would be the BEST way to address this concern?

  • A. Implement portfolio management.
  • B. Require monitoring of budget utilization.
  • C. Assign business sponsors to active projects.
  • D. Implement agile project methodology.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
shiowbah
9 months, 3 weeks ago
A. Implement portfolio management.
upvoted 1 times
...
SuperMax
10 months, 1 week ago
Selected Answer: B
B. Require monitoring of budget utilization. The best way to address the concern that all recently completed IT projects have exceeded their budgets is to require monitoring of budget utilization. By implementing a system for monitoring budget utilization throughout the project lifecycle, the IT director can track expenses, identify potential budget overruns early, and take corrective actions as needed to keep projects on track financially. This proactive approach enables better budget management and helps prevent projects from exceeding their allocated budgets.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel