Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months.
Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

  • A. Project risk management has been concluded with the project planning.
  • B. Project risk management happens at every milestone.
  • C. Project risk management is scheduled for every month in the 18-month project.
  • D. At every status meeting the project team project risk management is an agenda item.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Risk management is an ongoing project activity. It should be an agenda item at every project status meeting.
Incorrect Answers:
A: Risk management happens throughout the project as does project planning.
B: Milestones are good times to do reviews, but risk management should happen frequently.
C: This answer would only be correct if the project has a status meeting just once per month in the project.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Promz
10 months, 2 weeks ago
Correct answer B and not D. At every status meeting the project team project risk management is an agenda item. While it is important to discuss project risks at status meetings and have risk management as a regular agenda item, the best practice for comprehensive risk management typically involves more formal and structured reassessment at key project milestones rather than just during routine status meetings. Milestone reviews allow for a more in-depth analysis and evaluation of risks at critical points in the project timeline.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...