David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?
hammieo
Highly Voted 4 years, 10 months agokaykaymuon
Most Recent 4 months agoRadko96
6 months, 1 week agoWills3rd
10 months, 3 weeks agoJyLuv
11 months agoNdy
3 years, 1 month agoParth9
4 years, 3 months agoTTChizz
4 years, 5 months agouday1985
4 months, 1 week agoCL888
4 years, 3 months agotheApostle
5 years, 1 month agocatcklee
5 years, 4 months agoNdy
2 years ago