Exam CRISC topic 1 question 642 discussion

Actual exam question from Isaca's CRISC
Question #: 642
Topic #: 1
[All CRISC Questions]

After identifying new risk events during a project, the project manager's NEXT step should be to:

  • A. continue with a quantitative risk analysis
  • B. determine if the scenarios need to be accepted or responded to
  • C. continue with a qualitative risk analysis
  • D. record the scenarios into the risk register
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
NeilKK
Highly Voted 3 years, 9 months ago
Why not qualitative risk analysis? I think the answer should be D.
upvoted 5 times
CL888
3 years, 8 months ago
Yeah D
upvoted 4 times
...
...
Staanlee
Most Recent 8 months ago
Selected Answer: B
B. Determine if the scenarios need to be accepted or responded to. When new risk events are identified during a project, the next step should be to assess these risks to determine whether they need to be accepted (meaning no action is taken), or if a risk response plan should be developed and implemented. This assessment helps in deciding how to address these new risk events effectively. Continuing with a quantitative or qualitative risk analysis may be part of the process of assessing these new risks, but the initial step is to decide on a course of action based on their potential impact and likelihood. Recording the scenarios in the risk register is an important step but typically comes after the assessment and decision-making process.
upvoted 1 times
...
CbtL
1 year, 1 month ago
Selected Answer: D
We do not have enough information to decide if a quantitative or qualitative approach would be warranted. First action is to record the information, I believe. Selected D.
upvoted 2 times
...
Julianleehk
1 year, 2 months ago
Maybe A
upvoted 1 times
...
john_boogieman
1 year, 2 months ago
Selected Answer: D
First record and assess the risk and then make a decision about it.
upvoted 3 times
...
Boubou480
1 year, 3 months ago
Selected Answer: B
I would go for B. Risks identified during Project lifecycle don't need to be recorded in the Risk Register, so D is excluded.
upvoted 1 times
...
Ics2Pass
3 years, 2 months ago
Why not C? Qualitative analysis before Quantitative analysis?
upvoted 1 times
...
endyendytse
3 years, 2 months ago
risk action then risk register
upvoted 1 times
...
Rooks
3 years, 8 months ago
A ought to be the wrong answer. D should be the correct answer and then it needs to be decided whether it is acceptable or needs to be responded on which is option B.
upvoted 2 times
Rooks
3 years, 8 months ago
Okay after further reading - D is highlighting scenario which is not the case in the steam question. A seems to be the right answer then then will decide whether to accept or not.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago