Which of the following should be the PRIMARY driver for the prioritization of risk responses?

  • A. Residual risk
  • B. Inherent risk
  • C. Mitigation cost
  • D. Risk appetite
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
trev0r
3 days, 19 hours ago
Selected Answer: A
Residual risk is the risk that remains after controls have been implemented. It represents the actual, current level of exposure an organization faces. By focusing on residual risk, you can prioritize responses based on what is not yet adequately controlled. This ensures that resources are allocated to the most critical, remaining threats.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...