Which of the following is MOST useful when communicating risk to management?

  • A. Risk policy
  • B. Risk map
  • C. Maturity model
  • D. Audit report
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CbtL
7 months, 2 weeks ago
Selected Answer: B
Of the choices offered, agree with B.
upvoted 1 times
...
Ceecil1959
1 year, 7 months ago
Risk Map — a graphical depiction of a select number of a company's risks designed to illustrate the impact or significance of risks on one axis and the likelihood or frequency on the other. Risk mapping is used to assist in identifying, prioritizing, and quantifying (at a macro level) risks to an organization.
upvoted 1 times
...
aselunar
2 years, 5 months ago
R4-48 says key risk indicators. A risk map could include those. So of the choices given, perhaps this is correct.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.