Question #: 282
Topic #: 1
[All CGEIT Questions]

An enterprise embarked on an aggressive strategy requiring the implementation of several large IT projects impacting multiple business processes across all departments. Initially employees were supportive of the strategy, but there is growing fatigue and frustration with the ongoing new capabilities which must be learned. Which of the following would be the BEST action performed by senior management?

  • A. Establish "Reward and Recognition" efforts to boost employee morale.
  • B. Improve the system development life cycle (SDLC) process.
  • C. Incorporate an organizational change management program.
  • D. Assess current business and IT competencies.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
WongY
1 year, 1 month ago
See also Q258. Answer think should be C
upvoted 4 times
Ramye
9 months, 3 weeks ago
Q258 says - ‘which of the following should be in place prior to the start of the initiative?’ The key is prior to the start of the initiative where in this question the initiative already started, so think the answer given is right…
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago