A deficient control has been identified which could result in great harm to an organization should a low frequency threat event occur. When communicating the associated risk to senior management, the risk practitioner should explain:
A.
the current level of risk is within tolerance.
B.
mitigation plans for threat events should be prepared in the current planning period.
C.
an increase in threat events could cause a loss sooner than anticipated.
D.
this risk scenario is equivalent to more frequent, but lower impact risk scenarios.
This section is not available anymore. Please use the main Exam Page.CRISC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CbtL
8 months, 4 weeks ago