Exam CISA topic 1 question 724 discussion

Actual exam question from Isaca's CISA
Question #: 724
Topic #: 1
[All CISA Questions]

The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed. Which of the following should the audit manager do FIRST?

  • A. Extend the audit deadline.
  • B. Escalate to the audit committee.
  • C. Assign additional resources to supplement the audit.
  • D. Determine where delays have occurred.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TEC1
Highly Voted 2 years, 6 months ago
Selected Answer: D
D. Determine where delays have occurred. Before taking any action to address the delay in the audit project, it is important for the audit manager to determine the cause of the delay. This will help the audit manager to identify the root cause and make informed decisions on how to address the situation. Understanding where the delays have occurred will help the audit manager to better allocate resources and make changes to the project plan to ensure that the audit is completed on time. Only after the cause of the delay has been determined can the audit manager consider options such as extending the deadline, assigning additional resources, or escalating to the audit committee.
upvoted 6 times
...
JONESKA
Highly Voted 2 years ago
While extending the audit deadline (option A) or assigning additional resources (option C) might be viable options, it is essential to first determine the reasons for the delays to make informed decisions about the best course of action. Escalating to the audit committee (option B) should only be considered if there are significant issues or impediments that cannot be resolved at the managerial level. Therefore, the FIRST step for the audit manager is to determine where delays have occurred which is Option D, this will then enabling them to develop a well-informed and targeted plan to address the audit completion challenges.
upvoted 5 times
...
maxson69
Most Recent 1 month, 3 weeks ago
Selected Answer: D
Option D because understanding the cause is essential before deciding on the most effective corrective action.
upvoted 1 times
...
RS66
1 year ago
Selected Answer: D
D. The manager needs to determine the reason of the delay before taking action.
upvoted 2 times
...
starzuu
2 years ago
Selected Answer: D
i think its D.
upvoted 3 times
...
vipulsinghal2903
2 years, 10 months ago
A - you cannot extend audit deadline yourself C - Same reason as above. D - this will be done post completion.
upvoted 1 times
...
Deeplaxmi
2 years, 10 months ago
can anyone explain why this is the right answer?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...