Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model?

  • A. Describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).
  • B. Grouping the stakeholders based on their level of authority ("power") and their level or concern ("interest") regarding the project outcomes.
  • C. Influence/impact grid, grouping the stakeholders based on their active involvement ("influence") in the project and their ability to affect changes to the project's planning or execution ("impact").
  • D. Grouping the stakeholders based on their level of authority ("power") and their active involvement ("influence") in the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
A salience model defines and charts stakeholders' power, urgency, and legitimacy in the project.
The salience model is a technique for categorizing stakeholders according to their importance. The various difficulties faced by the project managers are as follows:
✑ How to choose the right stakeholders?
✑ How to prioritize competing claims of the stakeholders communication needs?
Stakeholder salience is determined by the evaluation of their power, legitimacy and urgency in the organization.
✑ Power is defined as the ability of the stakeholder to impose their will.
✑ Urgency is the need for immediate action.
✑ Legitimacy shows the stakeholders participation is appropriate or not.
The model allows the project manager to decide the relative salience of a particular stakeholder.
Incorrect Answers:
B: This defines the power/interest grid.
C: This defines an influence/impact grid.
D: This defines a power/influence grid.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Suchib
Highly Voted 1 year, 6 months ago
Is this in scope of CRISC?
upvoted 6 times
...
SuperMax
Most Recent 8 months, 2 weeks ago
Selected Answer: A
Ben works as a project manager for the MJH Project. In this project, Ben is preparing to identify stakeholders so he can communicate project requirements, status, and risks. Ben has elected to use a salience model as part of his stakeholder identification process. Which of the following activities best describes a salience model? A. Describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate). B. Grouping the stakeholders based on their level of authority ("power") and their level or concern ("interest") regarding the project outcomes. C. Influence/impact grid, grouping the stakeholders based on their active involvement ("influence") in the project and their ability to affect changes to the project's planning or execution ("impact"). D. Grouping the stakeholders based on their level of authority ("power") and their active involvement ("influence") in the project.
upvoted 1 times
...
examtp1
1 year, 2 months ago
This seems to be a PMP question
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...