What should be the PRIMARY objective for a risk practitioner performing a post-implementation review of an IT risk mitigation project?

  • A. Confirming that the project budget was not exceeded
  • B. Documenting project lessons learned
  • C. Validating that the risk mitigation project has been completed
  • D. Verifying that the risk level has been lowered
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CbtL
8 months, 2 weeks ago
Selected Answer: D
Agree with D. The point of the exercise is to lower risk.
upvoted 1 times
...
Koulyo
9 months, 1 week ago
I am telling you B is the answer.
upvoted 1 times
...
john_boogieman
10 months, 3 weeks ago
Selected Answer: D
The PRIMARY objective for a risk practitioner performing a post-implementation review of an IT risk mitigation project should be verifying that the risk level has been lowered.
upvoted 2 times
...
babaace
11 months, 3 weeks ago
The most important in an post-implementation review is lessons learned, so the correct answer is B
upvoted 1 times
babaace
11 months, 1 week ago
of course D is correct. I mixed things up with IRP and post-incident review
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...