Which of the following disaster recovery tests includes the operations that shut down at the primary site, and are shifted to the recovery site according to the disaster recovery plan?
rom an ISC2 CISS-ISSAP perspective, the scenario described aligns with C. Full-interruption test.
In a full-interruption test, all operations at the primary site are deliberately shut down to simulate a complete failure or disaster situation. These operations are then shifted and resumed at the recovery site according to the organization's established disaster recovery plan. This test helps evaluate the effectiveness of the plan in managing a full-scale disruption and measures how well systems can be brought up and functional at the recovery site.
Let's briefly describe the other options for clarity:
A. Structured walk-through test: A structured walk-through involves discussing and reviewing procedures without actual execution, typically involving key personnel going through various aspects of a plan or process.
B. Simulation test: A simulation test aims to replicate specific scenarios or events related to potential disasters but does not involve actually shutting down operations.
D. Parallel test: In parallel testing, both primary and secondary sites are operational simultaneously as part of normal business processes to assess functionality and performance without experiencing an actual disruption.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
74gjd_37
6 months, 1 week agoBanzaaai
1 year, 7 months ago