Question #: 32
Topic #: 8
[All CTAL-TM Questions]

Which of the following is a valid drawback of independent testing? 1 credit

  • A. Developer and independent testing will overlap and waste resources.
  • B. Developers loose the sense of responsibility and independent testers may become a bottleneck.
  • C. Independent testers need extra education and always cost more.
  • D. Independent testers will become a bottleneck and introduce problems in incident management.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Toprak
3 weeks, 1 day ago
Correct answer is D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.