Question #: 62
Topic #: 20
[All CTAL-TM Questions]

You are a test manager in charge of integration, system and acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards. The system should allow cash advances from €20 to €500, inclusively, for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard and Mastercard.
In the master test plan the following items are listed in the section named “items and/or features to be tested”:

I: All supported credit cards -

II: Language localization -

III: Valid and invalid advances -

IV: Usability -

V: Response time -
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits

  • A. All supported credit cards
  • B. Language localization
  • C. Valid and invalid advances
  • D. Usability
  • E. Response time
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Currently there are no comments in this discussion, be the first to comment!
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...