Actual exam question from ISTQB's CTFL v4.0
Question #: 51
Topic #: 1
[All CTFL v4.0 Questions]

Determining the schedule for each testing activity and test milestones for a test project, using activity estimates, available resources, and other constraints is a typical task performed during:

  • A. Test execution.
  • B. Test design.
  • C. Test analysis.
  • D. Test planning.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cb56e21
3 weeks, 5 days ago
Selected Answer: D
Un plan de prueba describe los objetivos, recursos y procesos para un proyecto de prueba.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...