Exam ITILFND V4 topic 1 question 171 discussion

Actual exam question from ITIL's ITILFND V4
Question #: 171
Topic #: 1
[All ITILFND V4 Questions]

Which statement about standard changes is CORRECT?

  • A. A full assessment should be completed each time the change is implemented
  • B. The change can be implemented with less testing if necessary
  • C. The appropriate change authority should be assigned to each type of change
  • D. The change does not require additional authorization
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KimoKono
1 month, 3 weeks ago
Selected Answer: D
Standard changes are pre-approved, routine changes that are well-understood and have low risk.
upvoted 1 times
...
Omega06g
9 months ago
A standard change requires no additional approvals, it’s low risk. A normal change requires approval and goes through the change enablement process (previously change control in V3.
upvoted 1 times
...
RickyQ
1 year, 4 months ago
A standard change is a low-risk, pre-authorized change that is well understood and fully documented, and can be implemented without needing additional authorization.
upvoted 3 times
...
bigpete975
2 years, 4 months ago
D is correct.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...