A company uses Power Apps and Microsoft Dataverse. The company has a managed solution in the production environment.

You make changes to the solution in the development environment. Some components are unused. The changes to the solution must be reflected in the production environment.

You need to ensure that all unused components are removed.

What should you do?

  • A. Patch the solution.
  • B. Update the solution.
  • C. Create a new solution.
  • D. Upgrade the solution.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ImissOOP
1 year, 6 months ago
I though you can't make changes to managed environment am i missing something
upvoted 1 times
...
voltaren
2 years, 4 months ago
Selected Answer: D
Upgrade https://learn.microsoft.com/en-us/power-apps/maker/data-platform/update-solutions
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...