Actual exam question from Microsoft's MB-320
Question #: 41
Topic #: 2
[All MB-320 Questions]

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.

The item has the following Lean setup:

• The setup uses a Lean schedule group with a throughput ratio=2
• The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1
• The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day)
• The throughput is 10 per hour

You need to set up a Discrete operation to mirror the item’s production flow activity.

What should you do?

  • A. Create a route with a runtime = 1. a process quantity = 6, and the operation's hours/time = 0.0167 (e.g. 1 hour/ 60 minutes).
  • B. Create a route with a runtime = 10. a process quantity = 6. and the operation's hours/time = 1.
  • C. Create a route with a runtime = 1. a process quantity = 1, and the operation s hours/time = 0.0167 (e.g. 1 hour/ 60 minutes).
  • D. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167 (e.g. 1 hour/ 60 minutes).
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MieNg
2 years ago
The correct answer is D. Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/ 60 minutes). This setup will match the throughput ratio of the Lean setup, which is 2. Since the Lean process activity has a runtime of 3 minutes per quantity, the Discrete operation should have twice the runtime, or 6 minutes per quantity. The process quantity is set to 1 to match the per quantity value of the Lean process activity. The operation’s hours/time is set to 0.0167 (e.g. 1 hour/ 60 minutes) to represent the time it takes to complete one unit of work in the Discrete operation.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...